Testing the data migration
After all prerequisites are complete, you can validate the migration setup for your node-based ElastiCache cluster using the AWS Management Console, ElastiCache API, or AWS CLI. The following example shows using the CLI.
Test migration by calling the test-migration command with the following
parameters:
-
--replication-group-idâ The ID of the replication group to which data is to be migrated. -
--customer-node-endpoint-listâ List of endpoints from which data should be migrated. List should have only one element.
The following is an example using the CLI.
aws elasticache test-migration --replication-group-id test-cluster --customer-node-endpoint-list "Address='10.0.0.241',Port=6379"
ElastiCache will validate migration setup without any actual data migration.