Skip to content

DTP_project_meeting,_April_27,_2010

Stephane Bouchet edited this page May 29, 2024 · 2 revisions

DTP project meeting, April 27, 2010

← Back to DTP Meetings, 2010 page

Attendees

  • Linda Chan (Actuate)
  • Brian "Fitz" Fitzpatrick (Red Hat)
  • Brian Payton (IBM)

Minutes

  • We need to triage the 1.8 and "no target milestone" defects
  • We need to have M7 changes in by this Thursday afternoon (which is the morning of April 30 in Beijing)
  • The RC1 integration build is Friday, May 14 (Beijing time)
  • Translation testing is starting next week
  • Fitz asked Brian P. to respond to a news group posting from Red Hat regarding the Query Plan
  • Fitz has updated the ramp-down plan

(Migrated from https://wiki.eclipse.org/DTP_project_meeting,_April_27,_2010

Clone this wiki locally